FeaturedGrowthTop Story

ARRMC’s new Central Utility Plant is ready to roll

Final switchgear means all systems go for added power and new chillers for the entire hospital.

Share:

A beautiful new, two-story Central Utility Plant on Murphy Road is powering ARRMC now that a final piece of switchgear has been installed.

The switchgear, which ensures safe, stable power for the hospital 24/7, was held up by about nine months, delaying the pavilion’s opening by about four months to Feb. 3, 2024.

The CUP will become fully functional Oct. 6, providing power and cooling systems for the entire hospital. Four giant Trane chillers stand ready to cool the hospital with up to 9,000 gallons of water per minute at full capacity. Each could cool the equivalent of 300 to 400 homes. Three will be used in the hottest parts of the summer; the fourth will act as a backup in case one of the other chillers breaks down.

CUP pumps
Two stories tall, the Central Utility Plant powers and cools the building.

“That redundancy is not a luxury Asante has had before and it’s not a luxury most hospitals have,” said Tim Ely, mechanical engineer who designed the mechanical portion of the CUP. “That has been built in intentionally because of the hot weather locally.”

Tall red pumps carry the warm water extracted from the building up to the chilling tower on the second floor, where mesh-like walls and giant fans move air through the water and release the heat as evaporation.

chilling tower
The chilling tower.

The fans, pumps and chillers run at variable speeds depending on how much cooling the hospital needs, “so we’re not using all that energy if we don’t need to,” Ely said. There’s also a separate heat exchanger that can be used in the spring and fall when some cooling is needed but not enough to fire up the big chillers.

The new system includes carbon filters that can be inserted into the air handlers to mitigate wildfire smoke, said Jeff Robbins, ARRMC Facilities manager.

Also included in the CUP are two new emergency power generators. Each produces 2 million watts (2,000 kilowatts) each, enough to run the chillers for the operating suites and critical care, something the hospital’s current generators can’t do.

The old chillers near the loading dock will be decommissioned. Asante will continue to use boilers located below the helipad to heat the hospital.

TIMELINE

Nov. 27: Dress rehearsal (technical)

Dec. 1: Department tours begin

Dec. 13: Dress rehearsal (clinical)

Jan. 16, 2024: Second dress rehearsal

Feb. 3, 2024: OPENING DAY, ground-floor move-in

Feb. 4: Floors 3 and 4 move-in

Feb. 5: Floors 5 and 6 move-in

Upcoming town halls
11 a.m.

Smullin Education Center and online (click on the link to join)

Oct. 25: Patient units, getting around, education and training.

Nov. 15: Dress rehearsal, education and training.

Dec. 14: Patient and equipment moves.

Questions? Email ne******@as****.org.

Tags: Central Utility Plant, occupancy, pavilion, update
For an IT pro, life took an interesting turn
Law enforcement aids in preventing workplace violence

If you have a question, please contact the author or relevant department directly.

Leave a Reply

Your email address will not be published. Required fields are marked *

Fill out this field
Fill out this field
Please enter a valid email address.
You need to agree with the terms to proceed

Categories

Popular related content